  • Capital Project Updates - Track and Field

    June 12, 2019: Work is in full swing at the high school stadium complex. Some highlights from the past few weeks include the creation of a temporary construction access point on Trolley Road, the removal of rubber surface from track oval and field event areas, the marking out of underground electric to the new scoreboard, removal of football goal posts and scoreboard flagpole, and the start of installation of silt fencing at required perimeter areas.

    Removal of Irrigation Stockpile Removal of football goalposts

    Silt fence installation Scoreboard flagpole removal