Capital Project Updates, August 2, 2019

Work at the site of the district’s new track and field complex keeps moving along! Recent developments include:

Temporary access to the project site has been moved to the high school parking lot, as access off Trolley Road has been closed.

The work area perimeter continues to be protected with temporary six-foot high fencing, and existing storm water catch basins continue to be protected with geotextile fabric and silt fencing.

Turf field drainage base stone had been previously installed; finish stone is in the process of being installed.

Scoreboard foundations and associated steel columns, as well as football goal footings, have been installed.

Steeplechase water hazard and related storm drainage connections have been installed.

All original track surfacing has been removed.

Click here to read updates since June: Capital Project Updates

New temporary entry Steeplechase pit installation

Scoreboard steel installation Track base installation